Nanaimo Regional Hospital Energy Plant

The Electrical Energy Centre was built to increase the amount of normal and emergency power available to the NRGH campus, to comply with regulatory, redundancy, and operational requirements. A new gas train was constructed to the south of the existing 25kV substation building and connected with the existing incoming gas service. A new fueling location complete with two underground fuel storage tanks was built adjacent to the parking lot. New electrical duct banks and vaults were also installed.